What a general contractor checks before it invites you to bid

The prequalification form is a list of things that went wrong with other subs. Each line, what it is really asking, the number that passes, and what to do when yours does not.

November 14, 2026 · 8 min read

Woman wearing headphones works at desk with laptop
Photo: Julio Lopez / Unsplash

A general contractor awarding a subcontract is managing the owner’s risk and its own. The prequalification form is how it does that, and every line on it exists because a GC somewhere got burned by a sub. Reading the form that way makes it easier to answer, because each answer is really “that will not happen with us, and here is why.”

Here is the form, line by line.

License and classifications

What it asks: Can you legally do this scope in this state?

What passes: An active license in the classification the scope needs, in every state the GC works in that you want to bid. A residential-only classification does not cover commercial work in some states, and a GC’s estimator will check the licensing board before the form comes back.

When yours does not: A lapsed or missing license is one of the six blockers in the Bid-Ready Score. Nothing else on the form matters until it is fixed, and the fix is administrative, so do it first.

Insurance limits and endorsements

What it asks: Will your coverage protect us if something goes wrong on our job?

What passes: General liability of at least $1 million per occurrence and $2 million aggregate is the common floor; larger GCs and public owners ask for more. Commercial auto, workers’ compensation, and an umbrella. The GC named as additional insured on a primary and non-contributory basis, with a waiver of subrogation, and your carrier willing to issue the certificate that way. A sub whose agent says the carrier “doesn’t do that endorsement” is a sub the GC cannot use.

When yours does not: This is a conversation with your insurance agent about the GC’s requirements, not the carrier’s standard form. Have the GC’s insurance exhibit in hand. Limits below $1M / $2M are a blocker.

Experience modification rate

What it asks: Do your people get hurt? And, on a wrap-up policy, what will you cost us?

What passes: An EMR of 1.0 is the industry average for your class. GCs look for 1.0 or below; many will not consider a sub above 1.2, and above 1.25 almost none will. A mod of 0.85 is a selling point.

When yours does not: The mod is a three-year lookback, so a bad year rolls off, and the story matters: a 1.1 from one claim three years ago, trending down, is different from a steady 1.1. Put the trend on the capabilities page and have the person who answers the form ready to tell it. The mod is a sales number, which is a separate piece on this site.

OSHA history and the safety program

What it asks: Same question as the mod, with different evidence.

What passes: No serious or willful citations in three years, recordables at or below the trade average, and a written safety program that is actually used, with a named person running it, OSHA 30 for superintendents and OSHA 10 for the field. The GC will ask for the OSHA 300 logs.

When yours does not: A willful citation in the last three years is a blocker; the rest is a program to build, and your insurance carrier’s loss-control people will often help build it for free, because it lowers their cost too.

Bonding capacity

What it asks: Can you be bonded for this job, with everything else you have going?

What passes: A letter from a surety stating a single-job limit and an aggregate limit, with the job you are bidding inside both. Not every commercial job is bonded, but the ones that move you up usually are, and a sub with no surety relationship cannot bid them.

When yours does not: The surety agent needs CPA-prepared financial statements and a current ratio above about 1.2 before writing the letter. That makes the next line the one to fix first.

Financial statements

What it asks: Will you finish the job and pay your suppliers?

What passes: Two to three years of statements prepared by a CPA. Reviewed or audited statements score highest; compiled statements are the floor for most GCs; internal statements from your own bookkeeping software usually do not pass. A current ratio above 1.2 and a line of credit sized to carry a job’s cash cycle.

When yours does not: No CPA-prepared statements is a blocker. Reviewed statements cost more than compiled; the step up is what unlocks the bonding letter and the larger GCs, so it pays for itself on the first job it makes possible.

Project list and references

What it asks: Have you done this scope, at this size, recently, and will someone we trust say so?

What passes: Three or more commercial projects in the last three years within a factor of two of the job you are bidding, with the building type, size, system, schedule and GC named. Three GC references who will take the call.

When yours does not: You cannot invent experience, but most subs understate what they have. A $400,000 tenant improvement for a GC counts even if the sub thinks of itself as residential. List everything commercial, with numbers.

Key personnel

What it asks: Who will actually run our job?

What passes: A project manager or superintendent who is not the owner, named, with years in the trade and projects run. A GC that sees the owner’s name in every box knows the sub cannot run two jobs at once.

When yours does not: This is the capacity question, and it is a hiring decision. It is also one of the things that decides which Ridgebeam package a sub starts in, because a desk that sets meetings for a sub that cannot staff a second job is hurting that sub’s name.

Why speed matters as much as the answers

Prequalification forms are a speed test as much as a qualification test. The estimator sends it to several subs and fills the slot with the one who returns it complete in a day. A form that goes to an info@ address and comes back half-filled four days later loses to a weaker sub who was ready.

The fix is a packet kept current: licenses, certificates, the mod letter, OSHA logs, the surety letter, statements, project sheets, references and personnel, in one folder, with one person who owns returning it. That is most of what RBP Risk does for a client every quarter, and the Bid-Ready Score is this form turned into a number.


Find out where you stand. It takes fifteen minutes.

One call with a Partner, and thirty-six questions you answer in your own time first. You leave with your Bid-Ready Score, the package that fits the size you want next, and the first three things to fix, whether or not you ever hire us.

No obligation. No pitch deck. If you are not ready for any of the packages yet, you will hear that too.