What a bond is
A surety bond is a three-party promise. The surety company guarantees to the general contractor (or the owner) that you, the subcontractor, will perform the contract and pay your suppliers and labor. If you do not, the surety steps in, finishes or pays, and then comes to you for the money. A bond is not insurance for you. It is a guarantee the surety makes about you, and the surety only makes it for companies it expects never to have to pay for.
There are usually two on a subcontract: a performance bond, covering completion, and a payment bond, covering your suppliers and subs. Each is typically written for the full contract value. The premium runs roughly one to three percent of the contract, paid by you and usually included in your bid.
Why the jobs that move you up require it
Public work almost always requires bonds from the GC, and the GC passes the requirement down to subs above a threshold, often $100,000 or $250,000 of subcontract value. Private owners and larger GCs require them on bigger scopes because a sub that fails mid-job is the single most expensive thing that happens on a commercial project.
So the jobs that would take a $2M sub to $4M are disproportionately the bonded ones. A sub that cannot be bonded is not competing for them, and the prequalification form finds that out early: “Bonding capacity, single and aggregate” is a line, and “none” is an answer that ends the conversation for that class of work.
What the surety looks at
A surety agent writes you a letter stating two numbers: the largest single job the surety will bond for you, and the total of all bonded work it will carry for you at once. Before writing it, the surety underwriter looks at what the industry calls the three Cs.
Capital. Your financial statements, prepared by a CPA, usually for two or three years. The surety reads working capital (current assets minus current liabilities) and net worth, and it reads them the way a bank does. A common rule of thumb puts single-job capacity around ten times working capital and aggregate around ten to twenty times, with wide variation. Internal statements from your bookkeeping software do not get a letter; compiled statements get a small one; reviewed statements get a real one; audited statements get the largest.
Capacity. Can you do the work? Your largest completed job, your project managers and superintendents, your equipment, your backlog and whether a new job fits in it, your experience with this kind of work. A sub whose largest job was $300,000 will not be bonded for $2M, whatever the balance sheet says.
Character. Your history of finishing jobs and paying people. References, credit, any liens or claims, and how the owners carry themselves. Sureties also ask for personal financial statements and a personal indemnity from the owners, which means the owners stand behind the bond with their own assets. That is normal, and a sub that balks at it will not be bonded.
The surety also checks the current ratio: current assets divided by current liabilities. Above 1.2 is comfortable, 1.0 to 1.2 gets questions, and below 1.0 usually gets a no.
How a sub with no bonding relationship gets one
In order, because each step depends on the one before.
- Get CPA-prepared statements. Compiled at minimum, reviewed if the target is real bonded work. Talk to the CPA about the surety’s view: a percentage-of-completion method for work in progress, a clean balance sheet, and a work-in-progress schedule the surety can read. This takes one year-end to do properly, so start before you need it.
- Fix the current ratio if it is under 1.2. Often this is a matter of how equipment debt is classified, or of paying down a line of credit before year-end.
- Find a surety agent, not a general insurance agent. Surety is a specialty, and the agent’s relationships with underwriters decide what letter you get. Your insurance agent, your CPA or your banker can usually refer one. In a Ridgebeam client workspace the surety agent has a seat, because the letter depends on documents three other advisors produce.
- Assemble the package: statements, the WIP schedule, a résumé of the company and its key people, a project list with sizes, references, a bank letter, personal financial statements for the owners, and a description of the work you want to bid.
- Ask for a starter program. A first letter is usually conservative, say $500,000 single and $1M aggregate. The surety grows the program as you complete bonded jobs and the statements improve. A sub that finishes three bonded jobs cleanly and shows the surety a stronger year-end usually gets the next letter without asking.
What raises the limit
Working capital, mostly. Retained earnings left in the company instead of distributed. A stronger statement level. Completed bonded work. A line of credit the surety can see. A second project manager, if capacity was the constraint. The surety agent will tell you which one is holding the number down if you ask, and most subs do not ask.
What lowers it, or ends it
Distributions that drain working capital at year-end. A claim on a bond. A job that goes over schedule and over budget on the WIP schedule. A change in ownership the surety did not hear about. Slow pay to suppliers that shows up as a lien. A surety that learns about a problem from someone other than you.
Where it sits in the Bid-Ready Score
Capital and bonding is fifteen of the hundred points: six for the statement level, five for a surety letter with single and aggregate limits, four for the current ratio. No CPA-prepared statements is one of the six blockers. A sub cannot start in Pipeline without bonding in place, because the jobs a Pipeline desk is working toward are the bonded ones.
A surety letter is also the single document on the prequalification form that says the most with the fewest words. A GC that reads “$1.5M single / $4M aggregate, [surety]” knows a professional underwriter has already looked at your statements, your capacity and your character and put money behind the answer. That is why the GC asks.