The Bid-Ready Score: a hundred-point view of where you stand
Half of the score is what a GC checks before inviting a sub. Half is what decides whether a sub that passes actually wins. Every line, every point, the six blockers, and what a score means for the package you start in.

Every Ridgebeam client starts with a number out of a hundred. It is not a grade. It is the general contractor’s prequalification form and the things that win work, turned into points, so a sub can see what is costing it jobs and what to fix first.
How the hundred is split
Half of the score covers what a GC checks before inviting a sub to bid: safety record, financial strength and bonding, and commercial experience. GCs look for an EMR at or below 1.0, and above 1.2 or 1.3 many will not consider a sub at all. GCs also typically ask for two to three years of financial statements. The other half covers what decides whether a sub that passes those checks actually wins: how many jobs it can run, whether someone owns the bidding and responds fast, and whether its website and bid packet look like a commercial contractor’s.
The six areas, line by line
Safety and risk, 20 points.
- EMR: 0.95 or below scores 8; 0.96 to 1.00 scores 6; 1.01 to 1.15 scores 3; above 1.15 scores 0.
- No serious or willful OSHA citations in three years, with recordables at or below the trade average: 5.
- Insurance that meets common GC requirements, GL $1M / $2M, auto, workers’ comp, umbrella: 4.
- A written safety program that is used, with a named person running it: 3.
Capital and bonding, 15 points.
- Financial statements: CPA-reviewed or audited scores 6; compiled 4; internal 1; none 0.
- A surety letter with single-job and aggregate limits: 5.
- Current ratio 1.2 or higher scores 4; 1.0 to 1.2 scores 2; below 1.0 scores 0.
Commercial experience, 15 points.
- Largest commercial job completed, scaled to the job size the sub wants next: 5.
- Share of revenue from commercial work: 50 percent or more scores 4; 20 to 49 percent scores 2; under 20 percent scores 0.
- Years in business: 5 or more scores 3; 3 to 4 scores 2; 2 scores 1.
- Three or more GC references from the last three years: 3.
Operational capacity, 15 points.
- Number of jobs the sub can run at once, with room for at least one more: 5.
- Project managers or superintendents run jobs, not only the owner: 4.
- Crews and backlog leave room for new work in the next six months: 3.
- Contractor licenses active in the states the sub wants to work in: 3.
Bid process, 20 points.
- Someone owns pursuing bids: a dedicated estimator or business developer scores 6; the owner part time 3; no one 0.
- Response time to an invitation to bid: acknowledged within two days and submitted on time scores 5; within a week 3; deadlines missed 0.
- Bids submitted a month, against what the package will bring (3, 6 or 10 or more): 5.
- Bids are tracked and the win rate is known: 4.
Marketing and presence, 15 points.
- Website, branding and copy aimed at GCs and commercial work, not homeowners: 5.
- A bid submission packet ready to send: capability statement, project sheets, safety and insurance documents: 5.
- Profiles current on GC bid platforms and vendor portals: 3.
- Commercial project photos and case studies: 2.
The six blockers
Any one of these places a client in Foundation, whatever the score, because GCs filter on them before a score matters:
- An EMR above 1.25
- GL limits below $1M per occurrence / $2M aggregate
- No CPA-prepared financial statements
- A missing or lapsed license
- A willful OSHA citation in the last three years
- Less than two years in business
Gaps in bid process and marketing are not blockers, because fixing them is Ridgebeam Partners’ work in every package.
What the score means for placement
| Package | Bid-Ready Score | Bid process score | Usual revenue | Other conditions |
|---|---|---|---|---|
| Foundation | Under 60, or any blocker | Any | Under $2.5M | Re-scored at months 3 and 6; moves to Bid-Ready at 60 or more with no blockers |
| Bid-Ready | 60–74 | Any; RBP builds it | $1M–$2.5M | No blockers |
| Pipeline | 75–84 | 12 or more of 20 | $2.5M–$5M | Someone owns bidding and responds within a week; bonding in place |
| Fractional CRO | 85 or higher | 16 or more of 20 | $5M–$10M | A dedicated estimator; can run several jobs at once |
The client starts at the lowest of three things: the package its score earns, the package its bid process can keep up with, and the number of jobs it can actually take on. Ridgebeam never sells more GC meetings than a client can bid on and build, because bids a sub cannot deliver hurt its name with GCs and lead to cancellations. A $4M sub with a score of 80 whose owner bids part time and can run two jobs at once starts in Bid-Ready, and moves to Pipeline once an estimator is in place.
A worked example
A commercial plumber, $2.1M last year, about 60 percent of it commercial. EMR 1.08, trending down from 1.22. No OSHA citations; a safety program on paper that nobody runs. GL at $1M / $2M with an umbrella. Compiled statements from a CPA; no surety letter; current ratio 1.3. Largest commercial job $350,000 for a regional GC, wants $750,000 jobs next. Eight years in business, two GC references. Can run three jobs at once, running two; one project manager besides the owner; licenses active. The owner chases bids part time, acknowledges invitations in about a week, submits two bids a month, does not track them. The website is residential; there is no packet; portal profiles are stale; a few project photos.
Scoring it: safety and risk 3 + 5 + 4 + 0 = 12. Capital and bonding 4 + 0 + 4 = 8. Commercial experience 3 + 4 + 3 + 2 = 12. Capacity 5 + 4 + 3 + 3 = 15. Bid process 3 + 3 + 2 + 0 = 8. Marketing 0 + 0 + 0 + 1 = 1. Total 56, no blockers.
Under 60 places the plumber in Foundation. The first three fixes are the ones that move the most points per dollar: name someone to own bids and the inbox (up to 6 points for the owner, 5 for response time), build the packet and the commercial website section (10 points), and get the surety letter the compiled statements and 1.3 current ratio already support (5 points). Those alone put the score above 75 before anything on the safety side changes, which is why the re-score at month three usually moves a Foundation client into Bid-Ready.
Why the score is built this way
Because a sub needs both halves. A sub with a perfect risk profile and no one calling GCs sits at home with a clean mod. A sub with a desk setting meetings and a 1.3 mod gets filtered out before the bid is read, and every meeting the desk set was wasted. The score makes both halves visible at once, and the plan it produces fixes them in the order that produces invitations soonest.
The thirty-six questions behind the score are answered before the Bid-Ready Assessment, in about ten minutes, and the call gives a provisional score and package in fifteen. The documents that confirm the answers come in the options review.