The cash cycle on a commercial job, and why it puts good subs out of business

Pay applications, thirty to sixty days, ten percent retainage until closeout. How the money on a commercial job actually moves, what it costs a sub to carry it, and the three things to set up before the first big one.

October 22, 2026 · 7 min read

Workers painting the floor of a large empty warehouse
Photo: Craftsman Concrete Floors / Unsplash

A residential job pays a deposit up front and the balance when the work is done. A commercial job pays you later, in pieces, and keeps some of it until months after you leave. The difference is the single most common reason a good subcontractor fails on its first large commercial job, and the general contractor’s prequalification form is largely designed to catch it before it happens.

How the money moves

The schedule of values. Before the job starts, you break the contract into line items with a dollar value for each: mobilization, rough-in by floor, trim, closeout. The GC approves it. Every month you bill against it.

The pay application. Around the twentieth of each month, you submit a pay application showing the percentage complete on each line, the amount earned to date, what was billed before, and what is due now. The GC reviews it, often cuts it, rolls it into its own application to the owner, and the owner’s lender or architect approves that.

Thirty to sixty days. The GC pays you when the owner pays the GC, which is typically thirty days after the GC’s application and often longer. Most subcontracts say so in a pay-when-paid or pay-if-paid clause. Work done in the first week of March is billed at the end of March and paid in May, if everything goes well.

Retainage. The GC holds back a percentage of every payment, usually ten percent, sometimes five after the job is half done, until the project is complete, closed out and accepted. On a $600,000 subcontract that is $60,000 of your money sitting with the GC until a closeout that can be months after your last day on site.

Lien waivers. Each payment comes with a waiver you sign giving up lien rights for the amount paid. Conditional waivers protect you until the check clears; unconditional ones do not. Signing the wrong one is a mistake subs make once.

What it costs to carry

Take a $600,000 subcontract over six months, with labor and material running evenly. Each month you spend about $100,000. The first pay application goes in at the end of month one and is paid, at best, at the end of month two. By then you have spent $200,000 and received $90,000, because ten percent was held. By the end of month three you have spent $300,000 and received $180,000.

Through the job you are carrying $100,000 to $150,000 of other people’s building with your money, and at the end, $60,000 is still held. If the owner’s lender slows a draw, add a month. If the GC cuts a pay application over a dispute, add more.

A sub that runs two of these at once is carrying a quarter million dollars. That is why the GC asks for financial statements, a current ratio and a line of credit. It has seen a sub run out of cash in month four and had to finish the scope with someone else at a premium.

Where subs get caught

  • Material up front. Switchgear, rooftop units, custom glazing: large deposits to suppliers before the first pay application, and the supplier’s terms are thirty days, not sixty.
  • Payroll weekly, pay apps monthly. Labor is paid every Friday regardless of when the owner’s draw lands.
  • The pay application cut. A GC that disputes percent complete or back-charges a cleanup item pays less than billed, and the shortfall comes out of the sub’s cash while it is argued.
  • Retainage forgotten. Subs that price a job at a thin margin and then realize ten percent is held until closeout have given the GC their margin as an interest-free loan.
  • Closeout delay. Punch lists, as-builts, warranties, the owner’s occupancy. Retainage releases when all of it is done for every trade, not when yours is.

Three things to set up before the first big one

1. A line of credit sized to the job. A bank line of credit, secured by receivables, that can carry the gap between payroll and pay applications. The bank will want CPA-prepared statements and a work-in-progress schedule, which is the same thing the surety and the GC want, so the statements do triple duty. Talk to the banker before you need the line, not during month three of the job.

2. A pay-application routine. Someone who knows the subcontract’s billing date, submits the application on that date with the schedule of values percentages that match the GC’s walk, attaches the conditional lien waiver and not the unconditional one, and follows up with the GC’s project accountant the week it is due. A pay application submitted three days late slips a full month.

3. Retainage in the price, and tracked. Know what retainage the subcontract carries before you price the job, carry its cost in the number, and track it as a separate receivable so it is billed at closeout instead of forgotten. Some states cap retainage or require it to be released by trade; your attorney’s seat in the workspace is where that question lives.

A fourth, for the ones that move you up: negotiate the subcontract’s payment terms before signing. Pay-if-paid clauses, retainage percentages and the closeout definition are all negotiable at the point of award, and never after.

Why this is on the prequalification form

Every line on the form that touches money exists because a sub ran out of it on someone’s job. Financial statements show whether you can carry the cycle. The current ratio shows whether you can carry it this quarter. The bonding letter shows that a surety has looked and agreed. References show that you have carried it before. A GC that sees all four invites the sub for the larger scope; a GC that sees none of them invites someone else and never says why.

Capital and bonding is fifteen of the hundred points in the Bid-Ready Score, and the CPA, the banker and the surety agent each have a seat in a Ridgebeam client’s workspace, because the three documents that get a sub through this gate are prepared by three different people who usually have never spoken to each other.


Find out where you stand. It takes fifteen minutes.

One call with a Partner, and thirty-six questions you answer in your own time first. You leave with your Bid-Ready Score, the package that fits the size you want next, and the first three things to fix, whether or not you ever hire us.

No obligation. No pitch deck. If you are not ready for any of the packages yet, you will hear that too.